Energy Curve Enhancement Blog 8 Including pumping
Based on experience and the energy curve database a typical primary crusher and the SAG mill can be assumed to be 1 km apart consuming about 0 40 kWh/t in conveying power Another 500 m of conveying can be assumed to be required for the pebble recycle but since the flowrate is only about 10% of the feed the contribution of the pebble recycle may be as low as 0 02 kWh/t For HPGR and